STAFF: Nick Ford, Development Manager
BACKGROUND:
The property owner, DCLI LLC, is requesting approval of a final plat for a ?224.5-acre campus located at 1 Deloitte Way, also known as Deloitte University. The purpose of this final plat is to incorporate the currently already platted area (Lot 1A) and unplatted area of Deloitte University (Lot 2A) into the thereby creating two platted lots for the campus. The final plat is the last legislative action required for the Deloitte Campus and is required before acceptance of any public infrastructure (i.e. Water, Sewer, etc...) from the Town and before issuance of a Certificate of Occupancy for the new buildings currently under construction. Infrastructure for the campus is nearing completion and the completion of the full project including all buildings and site work such as landscaping and hardscaping is expected to be finished near the end of the year 2025.
The subject property is zoned PD3-12 and PD3-12A and is currently under construction. The Planning and Zoning Commission approved the site plan for the Deloitte Expansion (Project STAR) on the 224.5-acre campus of the subject property on June 27, 2023.
The following is the approval chronology for the Deloitte Expansion:
1. Zoning Amendment - approved by the Commission on 1/11/2021; Town Council approved on 1/25/2021
2. Concept Plan - approved by the Commission on 11/29/2022; Town Council approved on 12/5/2022
3. Site plan - approved by the Commission on 6/27/2023; Town Council approved on 8/7/2023
4. Civil site construction - staff approval only. Issued for construction in June 2023
5. Building Permit - Staff approval only. Issued foundation package for construction in November 2023 and vertical...